2026 - W. Michigan Ave. Sidewalk Improvement Project Town of Southern Pines RFP
Work includes mobilization, 20 LF 30" fiber reinforced concrete curb and gutter (including installation of asphalt between existing road and new curb), 416 LF 4" x 5' fiber reinforced concrete sidewalk, 26 SY 6" x 5' fiber reinforced concrete sidewalk/driveway, 3 EA ADA directional ramp (including detectable warning domes), 1060 LF 30" fiber reinforced concrete curb and gutter (including installation of asphalt between existing road and new curb), 4 EA single 24x30 hood and grate catch basin, 3 EA flume inlet, 2 EA manhole cover and lid to existing drop box, 450 LF 4" x 5' fiber reinforced concrete sidewalk. See attached file.